|
|
|
DEQ Service Division |

The DEQ Technical Sales Service Division covers a wide spectrum of after the sales support. We do complete turn-key installations of vehicle gateway radiation monitors, support modifications and upgrades of existing systems, as well as troubleshooting in case of detector or electronic maintenance issues. Our service truck (shown above) is fully stocked with all of the tools and supplies we need to do onsite installations of radiation vehicle gateway monitoring systems. In addition to new vehicle gateway radiation monitor turn-key installations, we also provide re-installation of gateway monitors if they are damaged or need to be relocated. Click Here to view photos of our turn-key vehicle gateway radiation monitoring system installation.
|
Vehicle Gateway System Turn-Key Installation |
Description of Tasks Performed in Turn-Key Installation of Vehicle Gateway Monitoring Systems
High strength, fast-setting concrete with fiberglass reinforcement is used for the footers. Nominally, 3 1/2 to 4 1/2 cubic yards of concrete are required. Trenches, if required, are then dug from the far-side detector to the near-side detector. Conduit is installed in the trenches for power cables and signal cables. Also, trenches are dug for conduit going back to the scale office. Conduit is installed and wire pulled all the way back to the office. Conduit and wiring are then pulled through the office wall at the floor level or ceiling level to minimize visual impact. All trenches are then filled with either, dirt, asphalt patch, or concrete patch, depending on what material was trenched.
The computer and printer are mounted to the wall inside the scale office.
See
picture on right.
Cabling is brought from the building entry point to the computer location.
All cable runs meet national electrical codes.
Detectors and stands are lifted into place and bolted. Mounting of infrared
sensors and wiring is done on the detector stands.
In the scale office a 15 amp separate breaker is added to the electrical
panel.
For the price quoted, two items are required to be provided by the yard
owners. In the scale office building, a separate 15-amp circuit needs to be
provided. DEQ only needs an expansion slot at the electrical panel in the
building.
DEQ also asks for a heavy lifting device and operator. The lifting device
needs to be able to lift a minimum of 5000 pounds and a vertical lift of at
least 12 feet above grade. We estimate needing this device and operator for
a maximum of 1 to 1 1/2 hours.
Click Here to view photos of our turn-key vehicle gateway radiation monitoring system installation.